On February Arrow Construction Company entered into a threeyear construction contract to build a bridge for a price of
$ During costs of $ were incurred, with estimated costs of $ yet to be incurred. Billings of
$ were sent, and cash collected was $
In costs incurred were $ with remaining costs estimated to be $ billings were $ and
$ cash was collected. The project was completed in after additional costs of $ were incurred. The
company's fiscal yearend is December This project does not qualify for revenue recognition over time.
Required:
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
Prepare journal entries for to record the transactions described credit "Cash, Materials, etc." for construction costs incurred
b Prepare journal entries for to record the transactions described credit "Cash, Materials, etc." for construction costs incurred
a Prepare a partial balance sheet to show the presentation of the project as of December
b Prepare a partial balance sheet to show the presentation of the project as of December
Complete this question by entering your answers in the tabs below.
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
Note: Loss amounts should be indicated with a minus sign. Leave no cells blank.