On February 1,2024, Arrow Construction Company entered into a three-year construction contract to build a...

80.2K

Verified Solution

Question

Accounting

On February 1,2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of
$8,000,000. During 2024, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet tobe incurred. Billings of
$2,500,000 were sent, and cash collected was $2,250,000.
In2025, costs incurred were $2,500,000 with remaining costs estimated tobe $3,600,000.2025 billings were $2,750,000, and
$2,475,000 cash was collected. The project was completed in2026 after additional costs of $3,800,000 were incurred. The
company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
Calculate the amount of revenue and gross profit or loss tobe recognized in each of the three years.
2a. Prepare journal entries for 2024to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project asof December 31,2024.
3b. Prepare a partial balance sheet to show the presentation of the project asof December 31,2025.
image

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students