On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2024, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000.
In 2025, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2025 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2026 after additional costs of $3,820,000 were incurred. The companys fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!