On February 1, 2014, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total costs would be $4,000,000 and the project would be finished in 2016. Information relating to the costs and billings for this contract is as follows;

2014 2015 2016

Total costs incurred to date $1,500,000 $2,640,000 $4,600,000

Estimated cost to complete 2,500,000 1,760,000 -0-

Customer billings to date 2,200,000 4,000,000 5,600,000

Collections to date 2,000,000 3,500,000 5,500,000

Instructions

Fill in the correct amounts on the following schedule. For percent-of -completion accounting and for completed-contract accounting. Show your computations for the gross profit that should be recorded for 2014, 2015, and 2016.

Percentage-0f-Completion Completed-Contract

Gross Profit Gross profit

2014 ------------------------------------ 2014 --------------------------------

2015 ------------------------------------- 2015 --------------------------------

2016 ------------------------------------ 2016 -------------------------------

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students