Question

Accounting

On February 1, 2010, Marsh Contractors agreed to construct abuilding at a contract price of $5,800,000. Marsh estimated totalconstruction costs would be $4,000,000 and the project would befinished in 2012. Information relating to the costs and billingsfor this contract is as follows: 2014 2015 2016 Total costsincurred to date $1,500,000 $2,640,000 $4,600,000 Estimated coststo complete 2,500,000 1,760,000 -0- Customer billings to date2,200,000 4,000,000 5,600,000 Collections to date 2,000,0003,500,000 5,500,000

Instructions Fill in the correct amounts on the followingschedule.For percentage-of-completion accounting and forcompleted-contract accounting, show the gross profit that should berecorded for 2010, 2011, and 2012.

Percentage-of-Completion Revenue

2010:

2011:

2012:

Completed-Contract Revenue

2010:

2011:

2012:

Percentage-of-Completion Gross Profit

2010:

2011:

2012:

Completed-Contract Gross Profit

2010:

2011:

2012:

Calculate the Over/Under Billing for:

2010:

2011:

2012:

Answer & Explanation Solved by verified expert
3.6 Ratings (312 Votes)

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Marsh contractor
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2010 $1,500,000 $1,500,000 $4,000,000 37.50% $5,800,000 $2,175,000 $2,175,000 $675,000
2011 $1,140,000 $2,640,000 $4,400,000 60.00% $5,800,000 $3,480,000 $1,305,000 $165,000
2012 $1,960,000 $4,600,000 $4,600,000 100.00% $5,800,000 $5,800,000 $2,320,000 $360,000
Computation of Gross Profit - Revenue on completion - Marsh contractor
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2010 $1,500,000 $1,500,000 $4,000,000 $5,800,000 $0
2011 $1,140,000 $2,640,000 $4,400,000 $5,800,000 $0
2012 $1,960,000 $4,600,000 $4,600,000 $5,800,000 $1200,000

Please give thumbs up :-)


Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

In: AccountingOn February 1, 2010, Marsh Contractors agreed to construct abuilding at a contract price of...On February 1, 2010, Marsh Contractors agreed to construct abuilding at a contract price of $5,800,000. Marsh estimated totalconstruction costs would be $4,000,000 and the project would befinished in 2012. Information relating to the costs and billingsfor this contract is as follows: 2014 2015 2016 Total costsincurred to date $1,500,000 $2,640,000 $4,600,000 Estimated coststo complete 2,500,000 1,760,000 -0- Customer billings to date2,200,000 4,000,000 5,600,000 Collections to date 2,000,0003,500,000 5,500,000Instructions Fill in the correct amounts on the followingschedule.For percentage-of-completion accounting and forcompleted-contract accounting, show the gross profit that should berecorded for 2010, 2011, and 2012.Percentage-of-Completion Revenue2010:2011:2012:Completed-Contract Revenue2010:2011:2012:Percentage-of-Completion Gross Profit2010:2011:2012:Completed-Contract Gross Profit2010:2011:2012:Calculate the Over/Under Billing for:2010:2011:2012:

Other questions asked by students