On December 1, 2019, Montgomery Industries contracted with Gannett Construction to build a factory building. On that same day, Montgomery borrowed $500,000 on a construction loan at 10% interest to finance this project, and it immediately paid Gannett $120,000 as an initial payment on the contract. Construction of the factory building began on January 1, 2020, and Montgomery made the following additional payments to Gannett during 2020:

Date

Amount

March 1

$72,000

May 1

180,000

July 1

36,000

October 1

64,000

The project was completed on October 1, 2020.

Required:

Determine the cost of the factory building, including the amount of any capitalized interest

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students