Joni Steinberg wants to find the due date that gives her company's project a 99% chance of on-time completion. She needs to compute the Z value corresponding to 99%,as shown in figure 3-15. Mathematically, this is similar to example 10, except the unknown is now Z rather than the due date. please solve example 11

Project Management. 1. Expected completion time period for project is 15weeks 2.There's a 71.57% chance equipment in place, 16weeks 3. Critical path (A,C,E,G and H) 4. Not on critical path (B,D and F) and have slack time 5. See schedule start/end dates ) Table 3-3, Ex 6

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students