Accounting

Nova Company’s total overhead cost at various levels of activityare presented below:

MonthMachine-
Hours
Total
Overhead
Cost
April50,000$190,900
May40,000$164,400
June60,000$217,400
July70,000$243,900

Assume that the total overhead cost above consists of utilities,supervisory salaries, and maintenance. The breakdown of these costsat the 40,000 machine-hour level of activity is:

Utilities (variable)$60,000
Supervisory salaries(fixed)41,000
Maintenance (mixed)63,400
Total overhead cost$164,400

Nova Company’s management wants to break down the maintenancecost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $243,900 of overhead cost in Julywas maintenance cost. (Hint: to do this, it may be helpfulto first determine how much of the $243,900 consisted of utilitiesand supervisory salaries. Think about the behavior of variable andfixed costs.)

2. Using the high-low method, estimate a cost formula formaintenance in the form Y = a + bX.

3. Express the company’s total overhead cost in theform Y = a + bX.

4. What total overhead cost would you expect to beincurred at an activity level of 45,000 machine-hours?

Answer & Explanation Solved by verified expert
3.9 Ratings (569 Votes)
maintainance cost at july machine hour 70000 particulars 70000 Mhr Total overhead cost 24390000 less utilites cost 15per hour 70000150 10500000 supervisor salaries 4100000 maintainance cost 9790000 Utilities cost per hour    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

Nova Company’s total overhead cost at various levels of activityare presented below:MonthMachine-HoursTotalOverheadCostApril50,000$190,900May40,000$164,400June60,000$217,400July70,000$243,900Assume that the total overhead cost above consists of utilities,supervisory salaries, and maintenance. The breakdown of these costsat the 40,000 machine-hour level of activity is:Utilities (variable)$60,000Supervisory salaries(fixed)41,000Maintenance (mixed)63,400Total overhead cost$164,400Nova Company’s management wants to break down the maintenancecost into its variable and fixed cost elements.Required:1. Estimate how much of the $243,900 of overhead cost in Julywas maintenance cost. (Hint: to do this, it may be helpfulto first determine how much of the $243,900 consisted of utilitiesand supervisory salaries. Think about the behavior of variable andfixed costs.)2. Using the high-low method, estimate a cost formula formaintenance in the form Y = a + bX.3. Express the company’s total overhead cost in theform Y = a + bX.4. What total overhead cost would you expect to beincurred at an activity level of 45,000 machine-hours?

Other questions asked by students