Question

Accounting

Nova Companys total overhead cost at various levels of activity are presented below:

Month Machine- Hours Total Overhead Cost
April 46,000 $ 189,920
May 36,000 $ 166,220
June 56,000 $ 213,620
July 66,000 $ 237,320

Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is:

Utilities (variable) $ 43,200
Supervisory salaries (fixed) 68,000
Maintenance (mixed) 55,020
Total overhead cost $ 166,220

Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $237,320 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $237,320 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) I got the answer of $90,120 correct

2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.

3. Express the companys total overhead cost in the form Y = a + bX.

Variable Cost per Machine Hour Fixed Cost

Utility Cost

Supervisory Salaries Cost

Maintenance Cost

Total Overhead Cost Y=____+______X

4. What total overhead cost would you expect to be incurred at an activity level of 41,000 machine-hours?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students