Noting that activities B and C have activity A as a predecessor, what is the...

80.2K

Verified Solution

Question

Finance

image

Noting that activities B and C have activity A as a predecessor, what is the total expected time to complete this project for activities on the critical pathway using the PERT method? Predecessors a m Activity A b 11 7 9 B A 1 2 3 A 7 8 9 Select one: O a. 17 days O b. 10 days O C. 19 days O d. 11 days