Nettle Ltd is a firm of project managers which supports construction industry projects. It has two contracts (A and B), on which it commenced work in the year to 31 December 20X9; work will not be completed until the year to 31 December 20Y0. Relevant amounts on 31 December 20X9 are:
Contract
A
B
Costs to date
95,000
45,000
Recognised profits to date
5,500
-
Recognised losses to date
-
5,500
Progress payments invoiced to date
90,000
42,000
How much should Nettle disclose as contract assets in accordance with IFRS 15 'Revenue from Contracts with Customers'?
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!