Microsoft Project Case: Shoreline Stadium Case The G&E Company is preparing a bid to build the new 47,000-seat...

80.2K

Verified Solution

Question

General Management

Microsoft Project Case:

Shoreline Stadium Case

The G&E Company is preparing a bid to build the new47,000-seat Shoreline baseball stadium. The construction must starton July 1, 2020, and be completed in time for the start of the 2023season in April. A penalty clause of $250,000 per day of delaybeyond April 1st is written into the contract.

Percival Young, the president of the company, expressed optimismat obtaining the contract and revealed that the company could netas much as $3 million on the project. He also said if they weresuccessful, the prospects of future projects are bright since thereis a projected renaissance in building classic ball parks withmodern luxury boxes.

Questions:

Given the information provided in Table 6.3,using any project network computer program available to you toconstruct a network schedule for the stadium project and answer thefollowing questions:

  1. Will the project be able to be completed by the April 3deadline? How long will it take?
  2. What is the critical path for the project?
  3. Based on the schedule would you recommend that G&E pursuethis contact? Why? Include a one-page Gantt chart for the stadiumschedule.

TABLE 6.3 Shoreline StadiumCase

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

2

Clear stadium site

70 days

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

4

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

6

8

Install playing field

90 days

6

9

Construct upper steel bowl

120 days

6

10

Install seats

140 days

9

11

Build luxury boxes

90 days

9

12

Install jumbotron

30 days

9

13

Stadium infrastructure

120 days

9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

10

16

Build roof supports

90 days

4

17

Construct roof

180 days

16

18

Install roof tracks

90 days

14

19

Install roof

90 days

17, 18

20

Inspection

20 days

8, 11, 13, 15, 19


Attach the Microsoft Project file or a screenshot of theGantt chart.

Thank you, I will give you thumbs up!

Answer & Explanation Solved by verified expert
3.6 Ratings (339 Votes)
Before entering anything make the following two changesGo to Project Projet Information and change the startdate and current dateMake all tasks autoscheduled by default by clicking in the    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students