Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There...

90.2K

Verified Solution

Question

Accounting

Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the companys estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $3.60 to determine the bid price. Since our average cost is only $2.78 per square foot, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.

To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square feet 800 thousand square feet
Estimating and job setup Number of jobs 400 jobs
Working on nonroutine jobs Number of nonroutine jobs 100 nonroutine jobs
Other (costs of idle capacity and organization-sustaining costs) None

Note: The 100 nonroutine jobs are included in the total of 400 jobs. Both nonroutine jobs and routine jobs require estimating and setup.

Costs for the Year
Wages and salaries $ 480,000
Disposal fees 882,000
Equipment depreciation 108,000
On-site supplies 68,000
Office expenses 380,000
Licensing and insurance 580,000

Total cost $ 2,498,000

Distribution of Resource Consumption Across Activities
Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries 50 % 15 % 20 % 15 % 100 %
Disposal fees 70 % 0 % 30 % 0 % 100 %
Equipment depreciation 40 % 5 % 20 % 35 % 100 %
On-site supplies 70 % 20 % 10 % 0 % 100 %
Office expenses 15 % 35 % 20 % 30 % 100 %
Licensing and insurance 30 % 0 % 50 % 20 % 100 %

imageimage

Required: 1. Perform the first-stage allocation of costs to the activity cost pools Estimating Working on Removing Nonroutine Total Other Asbestos Job Setup Jobs 0 Wages and salaries 0 Disposal fees 0 Equipment depreciation On-site supplies Office expenses 0 Licensing and insurance 0 0 s 0 0 0 Total cost 2. Compute the activity rates for the activity cost pool Activity Cost Pool Activity Rate per thousand square feet Removing asbestos Estimating and job setup per job ng on nonroutine jobs per nonroutine job

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students