Craig, Inc., has provided the following information for one of its products for each hour of production:
Actual velocity: 200 units (per hour)
Move time: 18 minutes
Inspection time: 15 minutes
Rework time: 14 minutes
Required:
1. Calculate MCE. If required, round your answer to two decimal places.
2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places.
Theoretical cycle time
minutes
Actual cycle time
minutes
MCE
3. What if waste is reduced by 45 percent? New waste = minutes
What is the new MCE? If required, round your answer to two decimal places.
What is the new cycle time? minutes
MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 18 minutes Inspection time: 15 minutes Rework time: 14 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time minutes MCE 3. What if waste is reduced by 45 percent? New waste = 1 minutes What is the new MCE? If required, round your answer to two decimal places. What is the new cycle time? minutes
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!