Mastery Problem: Job Order Costing
Purl of Great Price Company
Maria Young is the sole stockholder of Purl of Great Price Company (POGP Company), which produces high-end knitted sweaters and sweater vests for sale to retail outlets. The company started in January of the current year, and employs three knitters (each of whom work 40 hours per week) and one office manager/knitting supervisor (this employee works 20 hours per week as office manager, and 20 hours per week as knitting supervisor). All wages are paid in cash at the end of each month.
Each knitter has a knitting machine that is used about 2/3 of the knitters time, the rest of the knitters time being involved in hand knitting and piecing together the garments. The company also has a packaging machine used to wrap the garments in plastic for shipping, which is operated by the office manager/knitting supervisor approximately 5 hours per week.
The knitting machines were purchased on January 1 of the current year, and cost $2,400 each, with an anticipated useful life of 10 years and no salvage value. The packaging machine was purchased on the same date and cost $4,800, with the same anticipated useful life and salvage value.
Nov. 30 Trial Balance
POGP Company Trial Balance November 30, 20Y8
Account Title
Debit
Credit
Cash
20,000
Accounts Receivable
1,000
Supplies
200
Materials
5,000
Work in Process
5,404
Equipment
12,000
Accumulated Depreciation-Equipment
825
Accounts Payable
150
Common Stock
10,000
Retained Earnings
12,000
Dividends
18,096
Sales
307,500
Cost of Goods Sold
255,040
Factory Overhead
15
Wages Expense
13,750
330,490
330,490
Predetermined Factory Overhead Rate
Since the company is more reliant on labor than machines, Maria decides to use direct labor hours (DLH) as the activity base for her predetermined factory overhead rate, rather than machine hours (MH).
Estimated Selected Amounts for the Year
Estimated depreciation on equipment
$1,200
Estimated total Office Manager/Knitting Supervisor wages
$42,000
Estimated office utilities
$4,000
Estimated factory utilities
$4,800
Estimated factory rent
$12,000
Activity Base Data
Estimated number of DLH for the year
5,000
Estimated number of MH for the year
3,500
Compute the predetermined factory overhead rate for the current year.
Materials Requisition
Date: Dec. 10
Req. No. 12255
Job No. 83
Description
Qty. Issued
Unit Price
Amount
Yarn type B
700 skeins
$5
$3,500
Total issued
$3,500
Time Ticket
No. 1255
Name:
Susan Blake
Work Description:
Knitting/piecing
Dates
Job No.
Hours Worked
Unit Price
Amount
12/01-12/15
62
65
$15
$975
12/16-12/31
83
103
15
1,545
Total Cost
$2,520
Time Ticket
No. 2274
Name:
Josh Porter
Work Description:
Knitting/piecing
Dates
Job No.
Hours Worked
Unit Price
Amount
12/01-12/15
62
75
$15
$1,125
12/16-12/31
83
88
15
1,320
Total Cost
$2,445
Time Ticket
No. 3923
Name:
Mary Jones
Work Description:
Knitting/piecing
Dates
Job No.
Hours Worked
Unit Price
Amount
12/01-12/15
62
60
$15
$900
12/16-12/31
83
109
15
1,635
Total Cost
$2,535
Job Cost Sheets
On December 10, POGP Company receives an order for 200 sweater vests and assigns Job 83 to the order. Review the Materials Requisition table to add the materials to the Job Cost Sheet for Job 83.
On December 15, review the Time Ticket tables to add the appropriate amount of direct labor and factory overhead costs to the Job Cost Sheet for Job 62 for the period December 1 through December 15.
On December 31, the last work day of the year for the knitters, review Time Ticket tables to add the appropriate amount of direct labor and factory overhead costs to the Job Cost Sheet for Job 83 for the period December 16 through December 31.
If there is no amount or an amount is zero, enter "0". If required, round your answers to the nearest cent.
Job 62
100 units:
Sweaters
Direct Materials
Direct Labor
Factory Overhead
Total
Balance Dec. 1
$5,000
$300
$104
$5,404
Dec. 15
fill in the blank cda4850adfeff86_1
fill in the blank cda4850adfeff86_2
fill in the blank cda4850adfeff86_3
fill in the blank cda4850adfeff86_4
Total Cost
$fill in the blank cda4850adfeff86_5
$fill in the blank cda4850adfeff86_6
$fill in the blank cda4850adfeff86_7
$fill in the blank cda4850adfeff86_8
Unit Cost
$fill in the blank cda4850adfeff86_9
Job 83
200 units:
Sweater vests
Direct Materials
Direct Labor
Factory Overhead
Total Job Cost
Balance Dec. 1
$0
$0
$0
$0
Dec. 10
fill in the blank cda4850adfeff86_10
fill in the blank cda4850adfeff86_11
fill in the blank cda4850adfeff86_12
fill in the blank cda4850adfeff86_13
Dec. 31
fill in the blank cda4850adfeff86_14
fill in the blank cda4850adfeff86_15
fill in the blank cda4850adfeff86_16
fill in the blank cda4850adfeff86_17
Total Cost
$fill in the blank cda4850adfeff86_18
$fill in the blank cda4850adfeff86_19
$fill in the blank cda4850adfeff86_20
$fill in the blank cda4850adfeff86_21
Journal
On December 10, POGP Company receives an order for 200 sweater vests and assigns Job 83 to the order. Review the Materials Requisition table to journalize the entry to record the addition of the materials to Work in Process. If an amount box does not require an entry, leave it blank.
Dec. 10
fill in the blank 29ec770c304a056_2
fill in the blank 29ec770c304a056_3
fill in the blank 29ec770c304a056_5
fill in the blank 29ec770c304a056_6
On December 15, review the Time Ticket tables to journalize the entry to record the addition of direct labor to Work in Process for the period December 1 through December 15. If an amount box does not require an entry, leave it blank.
Dec. 15
fill in the blank c4a52d00500afca_2
fill in the blank c4a52d00500afca_3
fill in the blank c4a52d00500afca_5
fill in the blank c4a52d00500afca_6
On December 15, review the Time Ticket tables to journalize the entry to record the addition of factory overhead to Work in Process for the period December 1 through December 15. If an amount box does not require an entry, leave it blank.
Dec. 15
fill in the blank 66477bf63fe5013_2
fill in the blank 66477bf63fe5013_3
fill in the blank 66477bf63fe5013_5
fill in the blank 66477bf63fe5013_6
On December 21, Job 62 is completed. Review the Job Cost Sheets and your journal entries. Journalize the entry to move the associated costs to the finished goods account. If an amount box does not require an entry, leave it blank.
Dec. 21
fill in the blank 27d7b602b04a061_2
fill in the blank 27d7b602b04a061_3
fill in the blank 27d7b602b04a061_5
fill in the blank 27d7b602b04a061_6
On December 22, 75 of the 100 sweaters from Job 62 are sold on account for $125 each. Journalize the following transactions:
a. The entry to record the sale.
b. The entry to record the transfer of costs from Finished Goods to Cost of Goods Sold.
If an amount box does not require an entry, leave it blank.
Dec. 22
fill in the blank f23bf5008fa0fc9_2
fill in the blank f23bf5008fa0fc9_3
fill in the blank f23bf5008fa0fc9_5
fill in the blank f23bf5008fa0fc9_6
Dec. 22
fill in the blank f23bf5008fa0fc9_8
fill in the blank f23bf5008fa0fc9_9
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!