Marvel Parts, Inc., manufactures auto accessories. One of the companys products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated with this level of production are:

Total Per Set of Covers
Direct materials $ 28,542 $ 14.20
Direct labor $ 8,040 4.00
Variable manufacturing overhead (based on direct labor-hours) $ 3,618 1.80
$ 20.00

During August, the factory worked only 1,200 direct labor-hours and produced 2,600 sets of covers. The following actual costs were recorded during the month:

Total Per Set of Covers
Direct materials (6,000 yards) $ 35,100 $ 13.50
Direct labor $ 10,920 4.20
Variable manufacturing overhead $ 5,460 2.10
$ 19.80

At standard, each set of covers should require 2.00 yards of material. All of the materials purchased during the month were used in production.

1.

Compute the materials price and quantity variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places. Round "Standard Price" and "Actual Price" answers to 2 decimal places.)

materials price variance:

materials quantity variance:

2.

Compute the labor rate and efficiency variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places. Round "Standard Rate" and "Actual Rate" answers to 2 decimal places.)

Labor rate variance:

materials quantity variance:

3.

Compute the variable overhead rate and efficiency variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places. Round "Standard Rate" and "Actual Rate" answers to 2 decimal places.)

variable overhead rate variance:

variable overhead efficiency variance:

Please show work (: thank you.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students