Question

Accounting

MANUFACTURING CYCLE EFFICIENCY

Kurena Company provided the following information on one of its factories:

Maximum units produced in a quarter: 180,000 units

Actual units produced in a quarter: 112,500 units

Hours of production labour in a quarter: 30,000 hours

Theoretical cycle time: 10 minutes per unit

Actual cycle time: 16 minutes per unit

Required:

1. Calculate the amount of processing time per unit and the amount of time per unit.

2. Calculate the MCE.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students