MAKING A BURRITO                                                                                       Names: _________________________ TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F,...

90.2K

Verified Solution

Question

Operations Management

MAKING ABURRITO                                                                                      Names: _________________________

TASKS

Predecessor

Task Time

A

Warm tortilla

-none

20 sec

B

Rice

-A

10 sec

C

Beans

-B

10 sec

D

Meat

-B

10 sec

E

Salsa

-C, D

10 sec

F

Cheese

-E

5 sec

G

Sour Cream

-E

10 sec

H

Lettuce

-E

10 sec

I

Wrap

-F, G, H

15 sec

J

Bag

-I

5 sec

K

Checkout/pay

-J

25 sec

All the informationneeded to solve the following questions is given.

  1. Assign tasks to workstations:

  1. Efficiency of your burrito line:

  1. Actual output per hour:

  1. What if demand were such that 200 / hour were needed?

  1. What is the maximum # of burritos that can be produced in anhour with these specific times/tasks?

Answer & Explanation Solved by verified expert
4.0 Ratings (541 Votes)
The network diagram for the activity is given as follows Eachtask is assigned to a workstation Time for each workstation ismentioned in the table in questionThe total    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students