La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of...
50.1K
Verified Solution
Question
Accounting
La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:
Quantity of direct labor used | 410 hrs. |
Actual rate for direct labor | $11.10 per hr. |
Bicycles completed in July | 190 bicycles |
Standard direct labor per bicycle | 2 hrs. |
Standard rate for direct labor | $11.30 per hr. |
a. Determine the direct labor rate variance, time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct labor rate variance | $fill in the blank 1 | |
Direct labor time variance | fill in the blank 3 | |
Total direct labor cost variance | $fill in the blank 5 |
b. How much direct labor should be debited to Work in Process? $fill in the blank 7
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.