Kerekes Manufacturing Corporation has prepared the followingoverhead budget for next month. Activity level 3,100...

Free

50.1K

Verified Solution

Question

Accounting

Kerekes Manufacturing Corporation has prepared the followingoverhead budget for next month. Activity level 3,100 machine-hoursVariable overhead costs: Supplies $ 15,810 Indirect labor 27,900Fixed overhead costs: Supervision 17,000 Utilities 6,500Depreciation 7,500 Total overhead cost $ 74,710 The company'svariable overhead costs are driven by machine-hours. What would bethe total budgeted overhead cost for next month if the activitylevel is 3,000 machine-hours rather than 3,100 machine-hours?Multiple Choice $72,650 $72,300 $73,300 $74,710

Answer & Explanation Solved by verified expert
4.1 Ratings (633 Votes)

The correct answer is $73,300 which is calculated as below:-
Variable overhead cost per 3,100 machine hours
Supplies          15,810            3,100       5.10 Per machine hours
Indirect labor          27,900            3,100       9.00 Per machine hours
Hence, variable overhead cost for 3,000 machine hours
Supplies              5.10            3,000 15,300
Indirect labor              9.00            3,000 27,000
Total variable overhead cost 42,300
Add : Fixed cost
Supervision          17,000
utilities            6,500
Depreciation            7,500 31,000
Total budgeted overhead cost 73,300

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

In: AccountingKerekes Manufacturing Corporation has prepared the followingoverhead budget for next month. Activity level 3,100 machine-hours...Kerekes Manufacturing Corporation has prepared the followingoverhead budget for next month. Activity level 3,100 machine-hoursVariable overhead costs: Supplies $ 15,810 Indirect labor 27,900Fixed overhead costs: Supervision 17,000 Utilities 6,500Depreciation 7,500 Total overhead cost $ 74,710 The company'svariable overhead costs are driven by machine-hours. What would bethe total budgeted overhead cost for next month if the activitylevel is 3,000 machine-hours rather than 3,100 machine-hours?Multiple Choice $72,650 $72,300 $73,300 $74,710

Other questions asked by students