Kelly-Lambing, Inc., a builder of government contracted smallships, has a steady workforce of 10 very skilled craftspeople.These workers can supply 2,500 labor-hours each per year.Kelly-Lambing is about to undertake a new contract, building a newstyle of boat. The first boat is expected to take 6,200 hours tocomplete. The firm thinks that 75% is the expected learning rate.What is the firm's "capacity" to make these boats-that is, how manyunits can the firm make in 1 year? If the operations manager canincrease the learning rate to 70% instead of 75 %, how many unitscan the firm make? (Round all numerical responses in thisexercise to the nearest whole number.)
Number of Boats @ Total time 75% and 70%
4
5
6
7
8