Job Order Cost Sheet Carlin Furniture Company refinishes and reupholsters furniture. Carlin Furniture uses a job order...

Free

50.1K

Verified Solution

Question

Accounting

Job Order Cost Sheet

Carlin Furniture Company refinishes and reupholsters furniture.Carlin Furniture uses a job order cost system. When a prospectivecustomer asks for a price quote on a job, the estimated cost dataare inserted on an unnumbered job cost sheet. If the offer isaccepted, a number is assigned to the job, and the costs incurredare recorded in the usual manner on the job cost sheet. After thejob is completed, reasons for the variances between the estimatedand actual costs are noted on the sheet. The data are thenavailable to management in evaluating the efficiency of operationsand in preparing quotes on future jobs. On July 6, 2016, anestimate of $3,003 for reupholstering a sofa and loveseat was givento Justin Flannigan. The estimate was based on the followingdata:

Estimated direct materials:
30 meters at $35 per meter$ 1,050
Estimated direct labor:
24 hours at $30 per hour720
Estimated factory overhead (75% of direct labor cost)540
Total estimated costs$2,310
Markup (30% of production costs)693
Total estimate$3,003

On July 10, the sofa and loveseat were picked up from theresidence of Justin Flannigan, 310 Suzuki Drive, Lubbock, TX, witha commitment to return it on September 7. The job was completed onSeptember 3.

The related materials requisitions and time tickets aresummarized as follows:

Materials Requisition No.Description    Amount
31015 meters at $35$525
31219 meters at $35665
Time Ticket No.Description    Amount
H5012 hours at $30$360
H5516 hours at $30480

Required:

Enter amounts as positive numbers.

1. Complete that portion of the job order costsheet that would be prepared when the estimate is given to thecustomer.

2. Record the costs incurred, and complete thejob order cost sheet.

JOB ORDER COST SHEET
CustomerJustin FlanniganDateJuly 6, 2016
Address310 Suzuki DriveDate wantedSept. 7, 2016
Lubbock, TXDate completedSept. 3, 2016
ItemReupholster Sofa and LoveseatJob. No.
ESTIMATE
Direct MaterialsDirect LaborSummary
AmountAmountAmount
30 Meters at $3524 Hours at $30Direct Materials
Direct Labor
Factory Overhead
TotalTotalTotal cost
ACTUAL
Direct MaterialsDirect LaborSummary
Mat. Req. No.DescriptionAmountTime Ticket No.DescriptionAmountItemAmount
31015 Meters at $35H5012 Hours at $30Direct Materials
Direct Labor
31219 Meters at $35H5516 Hours at $30Factory Overhead
TotalTotalTotal Cost

Feedback

1 & 2. Include the estimated and actual direct materials anddirect labor. Include the estimated and applied factoryoverhead.

Learning Objective 2, Learning Objective 3.

What is the best explanation for the variances between actualcosts and estimated costs. (For this purpose, assume that threemeters of materials were spoiled, the factory overhead rate hasbeen proved to be satisfactory, and an inexperienced employeeperformed the work.)

  1. The direct materials cost exceeded the estimate becausematerials were spoiled and the direct labor cost exceeded theestimate because additional hours of labor were used by aninexperienced employee.
  2. Management didn't provide enough direction to complete tasks onbudget.
  3. The direct materials cost exceeded the estimate becausematerials were spoiled.
  4. The direct labor cost exceeded the estimate because additionalhours of labor were used by an inexperienced employee.

Answer & Explanation Solved by verified expert
3.7 Ratings (507 Votes)

ESTIMATED JOB COST SHEET
Customer: Justin Flannigan
Address: 310 Suzuki Drive,Lubbock,TX
Item: Reupholster Sofa and Loveseat
PARTICULARS AMOUNT($)
Direct Material 1050
Direct Labour Hr 720
Estimated Factory Overhead 540
Total Cost 2,310
Mark Up (30% of cost) 693
Estimated Selling Price 3003
ACTUAL JOB COST SHEET
Customer Justin Flannigan
Address: 310 Suzuki Drive,Lubbock,TX
Item: Reupholster Sofa and Loveseat
PARTICULARS AMOUNT($) AMOUNT($)
Direct Material
Material 310 (15Mts*$35) 525
Material 312 (19Mts*$35) 665 1190
Material
Direct Labour Hr
H50 (12Hrs*$30) 360
H55 (16Hrs*30) 480 840
Estimated Factory Overhead 540
Total Cost 2570
Markup(30% on cost) 771
Selling Price 3341
There was variance between estimated and actual cost because of the following reason:

The direct materials cost exceeded the estimate because materials were spoiled. The direct labour cost exceeded the estimate because additional hours of labour were used by an inexperienced employee


Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students