Job Cost Sheet Estimated direct materials: 40 meters at $34 per meter Estimated...

50.1K

Verified Solution

Question

Accounting

Job Cost Sheet
Estimated direct materials:
40 meters at $34 per meter
Estimated direct labor:
28 hours at $20 per hour
Estimated factory overhead (75% of direct labor cost)
Total estimated costs
Markup (40% of production costs)
Total estimate
$1,360
On October 3, Jackson Consulting
proven to be satisfactory, and an inexperienced employee performed the work.) inexperienced employee. The factory overhead cost exceeded the estimate because an additional $60 of factory overhead was allocated because of the increase in direct labor.
b. Management didn't provide enough direction to complete tasks on budget.
c. The direct materials cost exceeded the estimate by $75 because 3 meters of materials were spoiled.
d. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee.
Select the correct answer from the above choices. signed a purchase contract, and the delivery and installation were completed on October 10.
The related materials requisitions and time tickets are summarized as follows:
\table[[Materials Requisition No.,Description,Amount],[112,20 meters at $34,$680
image

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students