Iron, Inc. designs and builds basketball gymnasiums. Each gymnasium is custom-built to individual customers specifications. Iron uses job-order costing to keep track of its costs. In February it worked on three jobs. Data for these jobs are as follows:
Job 177 | Job 178 | Job 179 | |
Balance 2/1 | $13,790 | $ 0 | $ 0 |
Direct Materials | 16,977 | 8,973 | 32,988 |
Direct Labor Cost | 22,251 | 7,720 | 46,608 |
Machine Hours | 400hrs. | 300hrs. | 2,000hrs. |
Overhead is applied to jobs at the rate of $22 per machine hour. By February 28, Job 178 is the only one unfinished. Jobs 177 and 179 are sold during February. Iron sells its product at cost plus 40%.
Calculate the balance of Work-in-Process on February 28.
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.