In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024
2025
2026
Cost incurred during the year
$ 2,400,000
$ 3,600,000
$ 2,200,000
Estimated costs to complete as of year-end
5,600,000
2,000,000
0
Billings during the year
2,000,000
4,000,000
4,000,000
Cash collections during the year
1,800,000
3,600,000
4,600,000
Westgate recognizes revenue over time according to percentage of completion.
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.
2024
2025
2026
Costs incurred during the year
$ 2,400,000
$ 3,800,000
$ 3,900,000
Estimated costs to complete as of year-end
5,600,000
4,100,000
0
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!