In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

70.2K

Verified Solution

Question

Accounting

In 2021, the Westgate Construction Company entered into acontract to construct a road for Santa Clara County for$10,000,000. The road was completed in 2023. Information related tothe contract is as follows:

202120222023
Cost incurred during the year$2,550,000$4,250,000$1,870,000
Estimated costs to complete as of year-end5,950,0001,700,0000
Billings during the year2,050,0004,750,0003,200,000
Cash collections during the year1,825,0004,100,0004,075,000

Westgate recognizes revenue over time according to percentage ofcompletion.

1. Calculate the amount of revenue and grossprofit (loss) to be recognized in each of the three years.

2021 2022 2023

Revenue ______ _______ ________

Gross P _______ _______ ________

2-a. In the journal below, complete thenecessary journal entries for the year 2021 (credit "Variousaccounts" for construction costs incurred).
2-b. In the journal below, complete the necessaryjournal entries for the year 2022 (credit "Various accounts" forconstruction costs incurred).
2-c. In the journal below, complete the necessaryjournal entries for the year 2023 (credit "Various accounts" forconstruction costs incurred).

3. Complete the information required below toprepare a partial balance sheet for 2021 and 2022 showing any itemsrelated to the contract.

4. Calculate the amount of revenue and grossprofit (loss) to be recognized in each of the three years assumingthe following costs incurred and costs to complete information.

202120222023
Costs incurred during the year$2,550,000$3,825,000$3,225,000
Estimated costs to complete as of year-end5,950,0003,125,0000

2021 2022 2023

Revenue ______ _______ ________

Gross P _______ _______ ________

5. Calculate the amount of revenue and grossprofit (loss) to be recognized in each of the three years assumingthe following costs incurred and costs to complete information.

202120222023
Costs incurred during the year$2,550,000$3,825,000$3,975,000
Estimated costs to complete as of year-end5,950,0004,150,0000

2021 2022 2023

Revenue ______ _______ ________

Gross P _______ _______ ________

Answer & Explanation Solved by verified expert
4.3 Ratings (783 Votes)
Answer Particulars 2021 2022 2023 Cost incurred during the year 2550000 4250000 1870000 Estimated costs to complete as of yearend 5950000 1700000 0 Billings during the year 2050000 4750000 3200000 Cash collections during the year 1825000 4100000 4075000 Calculate the amount of revenue and gross profit loss to be recognized in each of the three years 2021 2022 2023 Answer Particulars 2021 2022 2023 of    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students