In2018, the Westgate Construction Company entered into a contract toconstruct a road for Santa Clara County for $10,000,000. The roadwas completed in 2020. Information related to the contract is asfollows:


2018

2019

2020

Costincurred during the year

2,400,000

3,600,000

2,200,000

Estimatedcosts to complete as of year-end

5,600,000

2,000,000

0

Billingsduring the year

2,000,000

4,000,000

4,000,000

Cashcollections during the year

1,800,000

3,600,000

4,600,000


2-a. In thejournal below, complete the necessary journal entries (constructioncosts, progress billings, cash collections, gross profit/loss) forthe year 2018 (credit "Various accounts" for construction costsincurred).

2-b. In thejournal below, complete the necessary journal entries (constructioncosts, progress billings, cash collections, gross profit/loss) forthe year 2019 (credit "Various accounts" for construction costsincurred).

2-c. In thejournal below, complete the necessary journal entries (constructioncosts, progress billings, cash collections, gross profit/loss) forthe year 2020 (credit "Various accounts" for construction costsincurred).













































Answer & Explanation Solved by verified expert
3.8 Ratings (736 Votes)

2018 2019 2020
Contract price $        10,000,000 $        10,000,000 $        10,000,000
Actual costs to date $           2,400,000 $           6,000,000 $           8,200,000
Estimated costs $           5,600,000 $           2,000,000
total estimated costs $           8,000,000 $           8,000,000 $           8,200,000
Estimated gross profit (loss) $           2,000,000 $           2,000,000 $           1,800,000
revenue recognition
2018:(24000000/8000000)= 30%
30%*10000000= $           3,000,000
2019:(6000000/8000000)= 75%
(75%*10000000)-3000000= $           4,500,000
2020:10000000-3,000,000-4500000= $           2,500,000
Gross profit (loss) recognition:
2018:3000000-2400000= $              600,000
2019:4500000-3600000= $              900,000
2020:2500000-2200000= $              300,000
Journal entries
2018 2019 2020
Debit Credit Debit Credit Debit Credit
Construction in progress $           2,400,000 $           3,600,000 $        2,200,000
   Various accounts $           2,400,000 $        3,600,000 $        2,200,000
Accounts receivable $           2,000,000 $           4,000,000 $        4,000,000
   Billings on construction contract $           2,000,000 $        4,000,000 $        4,000,000
Cash $           1,800,000 $           3,600,000 $        4,600,000
Accounts receivable $           1,800,000 $        3,600,000 $        4,600,000
Construction In progress $              600,000 $              900,000 $            300,000
Cost of construction $           2,400,000 $           3,600,000 $        2,200,000
Revenue from long term contracts $           3,000,000 $        4,500,000 $        2,500,000

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students