ignore the scattered letters .thats the case stufy for the compulsory question . pleade solve...

90.2K

Verified Solution

Question

Finance

ignore the scattered letters .thats the case stufy for the compulsory question . pleade solve for me
image
image
GENERAL INSTRUCTIONS ANSWER QUESTION 1 AND ANY OTHER THREE FROM QUESTIONS 2 TO 7 READ THE CASE STUDY BELOW THE DUMASUA HOSPITAL PROJECT In the interest of better serving the public in the Brong Ahafo Region, the Dumasua Community in the Brong Region has decided to relocate a unit of the hospital from Dumasua to Fiapre Community a suburb within the Sunyani community that at present has no major medical facility. The move to Fiapre would mean constructing a new hospital unit and making it operational. Dr Edwin Osei, the Executive Director of the Hospital Board must prepare for a presentation, scheduled for next month, May 2022 to the General Health Secretariat Board of the hospital on the proposed project. Part of the presentation will address the specifics of the total project, including time and cost estimates for its completion. With the help of his staff, the Executive Director has identified 11 major project activities. He has also specified the immediate predecessors (those activities that must be completed before a given activity can begin) for each activity and the time estimates (weeks) to complete each activity. The results are as follows: Activity Description Immediate Predecessor Weeks A Select administrative and medical staff 12 B Select site and do site survey 9 C Select equipment A 10 D Prepare final construction plans and layout 10 B E Bring utilities to the site 24 Interview applicants and fill positions in nursing etc 10 Purchase and take delivery of equipment 35 Construct the hospital unit 40 Develop an information system A 15 Install the equipment E, B F A G H D I J SECTION A Compulsory QUESTION 1 Answer all questions a) Draw the Activity On Node (AON) network diagram for this hospital project including the estimated times for completion of each activity. 10 marks b) Determine the five paths for this project. 5 marks c) Define the critical path (CP) and indicate the CP for the project. 5 marks d) Calculate the Earliest Start and the Earliest Finish times of activities A, B, C, D and E of the project given the deterministic estimated completion times (Weeks). GENERAL INSTRUCTIONS ANSWER QUESTION 1 AND ANY OTHER THREE FROM QUESTIONS 2 TO 7 READ THE CASE STUDY BELOW THE DUMASUA HOSPITAL PROJECT In the interest of better serving the public in the Brong Ahafo Region, the Dumasua Community in the Brong Region has decided to relocate a unit of the hospital from Dumasua to Fiapre Community a suburb within the Sunyani community that at present has no major medical facility. The move to Fiapre would mean constructing a new hospital unit and making it operational. Dr Edwin Osei, the Executive Director of the Hospital Board must prepare for a presentation, scheduled for next month, May 2022 to the General Health Secretariat Board of the hospital on the proposed project. Part of the presentation will address the specifics of the total project, including time and cost estimates for its completion. With the help of his staff, the Executive Director has identified 11 major project activities. He has also specified the immediate predecessors (those activities that must be completed before a given activity can begin) for each activity and the time estimates (weeks) to complete each activity. The results are as follows: Activity Description Immediate Predecessor Weeks A Select administrative and medical staff 12 B Select site and do site survey 9 C Select equipment A 10 D Prepare final construction plans and layout 10 B E Bring utilities to the site 24 Interview applicants and fill positions in nursing etc 10 Purchase and take delivery of equipment 35 Construct the hospital unit 40 Develop an information system A 15 Install the equipment E, B F A G H D I J SECTION A Compulsory QUESTION 1 Answer all questions a) Draw the Activity On Node (AON) network diagram for this hospital project including the estimated times for completion of each activity. 10 marks b) Determine the five paths for this project. 5 marks c) Define the critical path (CP) and indicate the CP for the project. 5 marks d) Calculate the Earliest Start and the Earliest Finish times of activities A, B, C, D and E of the project given the deterministic estimated completion times (Weeks)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students