If a project has cash flows that alternate from negative to positive to negative again,...

70.2K

Verified Solution

Question

Finance

If a project has cash flows that alternate from negative to positive to negative again, the main concern in that situation would be:

A. the possibility that the NPV estimate will not take into account the time value of money

B. that the cash flow estimates are incorrect B. that networking capital needs are not being met

C. the possibility of multiple IRRs

D. that the IRR will be negative

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students