  1. If a division manager in a large organization reports to you that the NPV of a proposed project is positive, what should you do?

    A.

    All of the listed responses.

    B.

    None of the listed responses.

    C.

    Accept the project since firm value is maximized by accepting all positive NPV projects.

    D.

    Try to understand the underlying economics of why the NPV could be positive for your firm.

    E.

    Re-evaluate the project using an higher discount rate since the manager is probably too optimistic.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students