Question
General Management
Identify project of your choice and apply steps aproject manager can take to smooth a resource also provide ganttchart with smoothed resources
Answer & Explanation
Solved by verified expert
3.7 Ratings (642 Votes)
Project Title Planned maintenance of robotic machine lines in Steel Fabrication plant Steps for Project manager Step1 Collect a machine utilization plan from Production planning and Control PPC department This plan is essential to know the availability of Machine for preventive maintenance Step2a Schedule the plan for the available machines in spreadsheet Step2b Schedule the maintenance equipment and tools like Lubrication oil Grease Spanners Screw
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!