how to solve this question step by step. Calculate the number of workers that should have...

80.2K

Verified Solution

Question

Accounting

how to solve this question step by step.

Calculate the number of workers that should have beenavailable to process the July claims, and show allwork.

Standard time for processing per claim (simple claim)=36minutes

Standard time for processing per claim (complex claim)=1.25hours

Expected work hours per day 7.5 hours

Compensation cost per employee= $135 per day

Total working days=20

The number of July processed claims (simple)=3000

The number of July processed claims (complex)=960

Answer & Explanation Solved by verified expert
4.3 Ratings (885 Votes)
    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students