How is activity-based costing (ABC) cost driver activity rate computed? a. Cost pool total divided...

90.2K

Verified Solution

Question

Accounting

How is activity-based costing (ABC) cost driver activity rate computed?

a. Cost pool total divided by the number of cost driver events

b. Cost driver events divided by the number of cost pools

c. direct labor hours divided by the number of cost driver events

d. cost of goods sold divided by the number of calls driver events