How does one determine “slack time/float time†from a PERT
analysis? What does it mean when...
Free
80.2K
Verified Solution
Link Copied!
Question
Mechanical Engineering
How does one determine “slack time/float time†from a PERTanalysis? What does it mean when a task activity has no “slacktime/ float timeâ€
Answer & Explanation
Solved by verified expert
4.4 Ratings (598 Votes)
slack time= latest finish time of a activity - earliest finish
time of that activity &
earliest finish time=earliest starting time+time to do that
activity.
if an activity has no slack time then it means that activity is
critical activity. it means you can't delay that activity while
completing project.if this activity delays then completing time of
project would be increased.
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!