How does one determine “slack time/float time” from a PERT analysis? What does it mean when...

Free

80.2K

Verified Solution

Question

Mechanical Engineering

  1. How does one determine “slack time/float time” from a PERTanalysis? What does it mean when a task activity has no “slacktime/ float time”

Answer & Explanation Solved by verified expert
4.4 Ratings (598 Votes)

slack time= latest finish time of a activity - earliest finish time of that activity &

earliest finish time=earliest starting time+time to do that activity.

if an activity has no slack time then it means that activity is critical activity. it means you can't delay that activity while completing project.if this activity delays then completing time of project would be increased.


Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students