Hi-Tek Manufacturing, Incorporated, makes two types of industrial component partsthe B300 and the T500. An...

60.1K

Verified Solution

Question

Accounting

Hi-Tek Manufacturing, Incorporated, makes two types of industrial component partsthe B300 and the T500. An absorption costing income statement for the most recent period is shown:

Hi-Tek Manufacturing Incorporated Income Statement
Sales $ 1,761,900
Cost of goods sold 1,224,790
Gross margin 537,110
Selling and administrative expenses 570,000
Net operating loss $ (32,890)

Hi-Tek produced and sold 60,500 units of B300 at a price of $21 per unit and 12,600 units of T500 at a price of $39 per unit. The companys traditional cost system allocates manufacturing overhead to products using a plantwide overhead rate and direct labor dollars as the allocation base. Additional information relating to the companys two product lines is shown below:

B300 T500 Total
Direct materials $ 400,800 $ 162,200 $ 563,000
Direct labor $ 120,600 $ 43,000 163,600
Manufacturing overhead 498,190
Cost of goods sold $ 1,224,790

The company has created an activity-based costing system to evaluate the profitability of its products. Hi-Teks ABC implementation team concluded that $52,000 and $107,000 of the companys advertising expenses could be directly traced to B300 and T500, respectively. The remainder of the selling and administrative expenses was organization-sustaining in nature. The ABC team also distributed the companys manufacturing overhead to four activities as shown below:

Activity Cost Pool (and Activity Measure) Manufacturing Overhead Activity
B300 T500 Total
Machining (machine-hours) $ 203,490 90,700 62,300 153,000
Setups (setup hours) 133,200 73 260 333
Product-sustaining (number of products) 100,600 1 1 2
Other (organization-sustaining costs) 60,900 NA NA NA
Total manufacturing overhead cost $ 498,190

Required:

1. Compute the product margins for the B300 and T500 under the companys traditional costing system.

2. Compute the product margins for B300 and T500 under the activity-based costing system.

3. Prepare a quantitative comparison of the traditional and activity-based cost assignments.

For part 3.)

image

Prepare a quantitative comparison of the traditional and activity-based cost assignments. (Round your intermediate calculations to 2 decim

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students