Hector Company purchased land for an office site by paying $900,000 cash on January 1,...
80.2K
Verified Solution
Question
Accounting
Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January 1 and finished December 31, 2019. The following expenditures were incurred for construction
Date | Expenditures |
January 1, 2019 | $600,000 |
April 1, 2019 | $840,000 |
October 1, 2019 | $1,500,000 |
December 1, 2019 | $2,400,000 |
Calculate the weighted-average accumulated expenditure on the project during the year 2019 was:
a. $1,735,000
b. $1,805,000
c. $1,880,000
d. $1,800,000
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.