Given the following information.
| |
Maximum capacity (labor hours): | 350 hours per week |
Effective capacity ratio: | 70% |
Actual time worked: | 243 hours per week over the last two weeks |
On-time delivery %: | 60 percent of the jobs are being completed on time |
|
a. Calculate the effective capacity and actual utilization. (Round your answers to 2 decimal places.)
b. Do we need to add more capacity?