Question

Accounting

Galanis Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Calculate the throughput time and Manufacturing Cycle Efficiency for this order.

Wait time 24.7 hours

Process time 1.4 hours

Inspection time 0.4 hours

Move time 3.6 hours

Queue time 8.7 hours