For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...

Free

90.2K

Verified Solution

Question

General Management

For this assignment, create a Project Schedule, and list the 20+activities required to complete the house that you identified inyour Unit IV Project Budget. Assign a schedule to all identifiedactivities. Please be sure to reserve two weeks for contingencies.In other words, you should schedule all the activities and setaside two weeks for contingencies. The entire project (includingthe two-week contingency period) should equal 24 months

Unit 4 Project:

Activity DescriptionEst $
Architectural Design50,000
Procurement of machinery60,000
Hiring Labor120,000
Interior Design15,000
Windows and Doors20,000
HVAC40,000
Framing130,000
Lumber80,000
Drywall45,000
Interior Decorator and Decorations20,000
Work and Environmental Permits25,000
Landscaping30,000
Scaffolding Rental25,000
Paint and Wood Finishing40,000
Plumbing30,000
Electrical30,000
Lighting Fixtures20,000
Site Security20,000
Roofing40,000
Flooring30,000
Exterior Rock50,000
Plumbing Fixtures20,000
Cabinetry40,000
Concrete80,000
Material Storage10,000
Cost of Construction1,070,000
Contingency (2%)20,400
Total1,090,400

Answer & Explanation Solved by verified expert
3.8 Ratings (559 Votes)

Activity Description Start Date End Date Days to complete Est $
Architectural Design 01-05-2018 15-05-2018 14 50,000
Procurement of machinery 15-05-2018 30-05-2018 15 60,000
Hiring Labor 31-05-2018 10-06-2018 10 1,20,000
Interior Design 11-06-2018 26-07-2018 45 15,000
Windows and Doors 25-07-2018 23-09-2018 60 20,000
HVAC 20-09-2018 30-10-2018 40 40,000
Framing 31-10-2018 28-02-2019 120 1,30,000
Lumber 10-02-2019 12-03-2019 30 80,000
Drywall 15-03-2019 29-04-2019 45 45,000
Interior Decorator and Decorations 30-04-2019 29-07-2019 90 20,000
Work and Environmental Permits 16-05-2018 26-05-2018 10 25,000
Landscaping 20-05-2018 27-05-2018 7 30,000
Scaffolding Rental 30-07-2019 06-08-2019 7 25,000
Paint and Wood Finishing 06-08-2019 20-10-2019 75 40,000
Plumbing 15-10-2019 14-11-2019 30 30,000
Electrical 10-11-2019 10-12-2019 30 30,000
Lighting Fixtures 01-12-2019 16-12-2019 15 20,000
Site Security 15-12-2019 25-12-2019 10 20,000
Roofing 26-12-2019 09-02-2020 45 40,000
Flooring 10-02-2020 25-02-2020 15 30,000
Exterior Rock 05-02-2020 20-02-2020 15 50,000
Plumbing Fixtures 20-02-2020 27-02-2020 7 20,000
Cabinetry 25-02-2020 06-03-2020 10 40,000
Concrete 05-03-2020 20-03-2020 15 80,000
Material Storage 21-03-2020 15-04-2020 25 10,000
Cost of Construction 10,70,000
Contingency (2%) 16-04-2020 30-04-2020 14 20,400

Total

Below is the PROJECT SCHEDULE

Project Start Date-1-05-2018

Project End Date-30-4-2018

The overall time of completion (24 months) includes the contingency time (2 weeks) as well

10,90,400

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students