Fogerty Company makes two productsHubs and Sprockets. Data regarding the two products follow: ...

60.1K

Verified Solution

Question

Accounting

Fogerty Company makes two productsHubs and Sprockets. Data regarding the two products follow:

Direct Labor-Hours per Unit Annual Production
Hubs 0.50 25,000 units
Sprockets 0.10 40,000 units

Additional information about the company follows:

  1. Hubs require $29 in direct materials per unit, and Sprockets require $16.
  2. The direct labor wage rate is $17 per hour.
  3. Hubs are more complex to manufacture than Sprockets and they require special processing.
  4. The companys activity-based absorption costing system has the following activity cost pools:

Activity Cost Pool (and Activity Measure) Estimated Overhead Cost Expected Activity
Hubs Sprockets Total
Machine setups (number of setups) $ 26,910 130 104 234
Special processing (machine-hours) $ 156,000 3,900 0 3,900
General factory (Direct labor-hours) $ 99,000 12,500 4,000 16,500

Required:

1. Compute the unit product cost for Hubs and Sprockets using activity-based absorption costing.

Compute the unit product cost for Hubs and Sprockets using activity-based absorption costing. (Do not round intermediate calculations. Round your answers to 2 decimal places.)

Hubs Sprockets
Direct materials
Direct labor
Manufacturing overhead
Unit product cost $0.00 $0.00

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students