FMCG program’s program manager has reported the following BAC, EAC information. Highlight the reasons/possibilities why the BAC/EAC...

70.2K

Verified Solution

Question

General Management

FMCG program’s program manager has reported the following BAC,EAC information. Highlight the reasons/possibilities why theBAC/EAC could be as per chart below.

Point of Time 2 months 4 months 6 months 8 months 10 months

BAC 100,000 100,000 100,000 120,000 135,000

EAC 60,000 120,000 150,000 150,000 140,000

Answer & Explanation Solved by verified expert
4.0 Ratings (690 Votes)
EAC BAC cumulative CPI at 2 months CCPI 10000060000 166 at 4 months CCPI 100000120000 0833 at 6 months CCPI 100000150000 06666 at 8 months CCPI 120000150000 08 at 10 months CCPI    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students