Find the critical path and critical time for thefollowing business network:
Activity Pre. Act. Duration
A - 18
B A 25
C B 1
D C 14
E C 12
F E 1
G D 18
H E,G 3
I C 14
J F,I 16
K J 5
L J 25
M H 22
N K,L 13

Answer & Explanation Solved by verified expert
4.2 Ratings (468 Votes)
Dummy activity an activitywhich is used to show logic dependance or relationship between    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students