February 1, 2018, Salisbury Company purchased land for the future factory location at a cost...
50.1K
Verified Solution
Question
Accounting
February 1, 2018, Salisbury Company purchased land for the future factory location at a cost of $77,000. The dilapidated building that was on the property was demolished so that construction could begin on the new factory building. The new factory was completed on November 1, 2018. Costs incurred during this period were:
Item | Amount |
Demolition dilapidated building | $3,800 |
Architect Fees | $11,250 |
Legal Fees - for title search | $1,350 |
Interest During Active Construction Period | $5,025 |
Real estate transfer tax | $1,425 |
Construction Costs | $605,000 |
Using this information, how much should be recorded as the cost of the land?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.