Fast Company has established the following overhead cost pools and cost drivers for the month of May:
Cost Pool | Overhead Costs | Cost Driver Levels |
---|
Purchase orders | $ 19,080 | 30 | orders |
---|
Machine setups | 42,000 | 100 | setups |
---|
Electricity | 20,000 | 20,000 | kilowatt hours |
---|
The following information pertains to the actual consumption of activity resources for two sample jobs completed during May.
| Job M1 | Job M2 |
---|
Number of units produced | 480 | 960 |
---|
Number of purchase orders | 20 | 15 |
---|
Number of setups | 25 | 15 |
---|
Number of kilowatt hours | 480 | 960 |
---|
What is the activity-based overhead rate per purchase order?