Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies...

Free

80.2K

Verified Solution

Question

Accounting

Exercise 2-15 Plantwide and Departmental Predetermined OverheadRates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4]

[The followinginformation applies to the questions displayedbelow.]

Delph Company uses ajob-order costing system and has two manufacturingdepartments—Molding and Fabrication. The company provided thefollowing estimates at the beginning of the year:

  

MoldingFabricationTotal
Machine-hours31,00041,00072,000
Fixedmanufacturing overhead costs$740,000$210,000$950,000
Variablemanufacturing overhead cost per machine-hour$5.50$5.50

  

During the year, thecompany had no beginning or ending inventories and it started,completed, and sold only two jobs—Job D-70 and Job C-200. Itprovided the following information related to those two jobs:

  

Job D-70:MoldingFabricationTotal
Direct materialscost$378,000$322,000$700,000
Direct laborcost$230,000$160,000$390,000
Machine-hours24,0007,00031,000

  

Job C-200:MoldingFabricationTotal
Direct materialscost$290,000$230,000$520,000
Direct laborcost$160,000$270,000$430,000
Machine-hours7,00034,00041,000

Delph had nounderapplied or overapplied manufacturing overhead during theyear.

Exercise 2-15 Part 2

2. Assume Delph usesdepartmental predetermined overhead rates based onmachine-hours.

a. Compute thedepartmental predetermined overhead rates.

b. Compute the totalmanufacturing cost assigned to Job D-70 and Job C-200.

c. If Delphestablishes bid prices that are 140% of total manufacturing costs,what bid prices would it have established for Job D-70 and JobC-200?

d. What is Delph’scost of goods sold for the year?

Answer & Explanation Solved by verified expert
3.8 Ratings (499 Votes)

2a Departmental predetermined overhead rates
Molding department
Fixed manufacturing overhead (740,000/31000) 23.87
Variable manufacturing overhea 5.50
predetermined overhead rate 29.37
Fabrication department
Fixed manufacturing overhead (210000/41000) 5.12
Variable manufacturing overhea 5.50
predetermined overhead rate 10.62
Molding department 29.37 per MH
Fabrication department 10.62 per MH
2b) total manufacturing cost assinged
job D-70
molding Fabrication total
Direct materials cost 378,000 322,000 700,000
direct labor cost 230,000 160,000 390,000
overhead assigned
molding 704903 704903
Fabrication 74354 74354
total manufacturing cost 1,312,903 556,354 1,869,257
job c-200
molding Fabrication total
Direct materials cost 290,000 230,000 520,000
direct labor cost 160,000 270,000 430,000
overhead assigned
molding 32.43*8000 205596.8 205596.8
Fabrication 11.59*28000 12.84*30,000 361146.3 361146.3
total manufacturing cost 655,597 861,146 1,516,743
total manufacturing
cost
job D-70 1,869,257
Job C-200 1,516,743
2c) Bid price
cost
job D-70 2,616,960
Job C-200 2,123,440
2d) cost of goods sold 3,386,000

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students