Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies...

Free

80.2K

Verified Solution

Question

Accounting

Exercise 2-15 Plantwide and Departmental Predetermined OverheadRates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4]

[The followinginformation applies to the questions displayedbelow.]

Delph Company uses ajob-order costing system and has two manufacturingdepartments—Molding and Fabrication. The company provided thefollowing estimates at the beginning of the year:

  

MoldingFabricationTotal
Machine-hours31,00041,00072,000
Fixedmanufacturing overhead costs$740,000$210,000$950,000
Variablemanufacturing overhead cost per machine-hour$5.50$5.50

  

During the year, thecompany had no beginning or ending inventories and it started,completed, and sold only two jobs—Job D-70 and Job C-200. Itprovided the following information related to those two jobs:

  

Job D-70:MoldingFabricationTotal
Direct materialscost$378,000$322,000$700,000
Direct laborcost$230,000$160,000$390,000
Machine-hours24,0007,00031,000

  

Job C-200:MoldingFabricationTotal
Direct materialscost$290,000$230,000$520,000
Direct laborcost$160,000$270,000$430,000
Machine-hours7,00034,00041,000

Delph had nounderapplied or overapplied manufacturing overhead during theyear.

Exercise 2-15 Part 1

Required:

1. Assume Delph uses aplantwide predetermined overhead rate based on machine-hours.

a. Compute theplantwide predetermined overhead rate.

b. Compute the totalmanufacturing cost assigned to Job D-70 and Job C-200.

Answer & Explanation Solved by verified expert
4.3 Ratings (774 Votes)

a)

Calculation of Plantwide Predetermined Overhead Rate
Total fixed cost $             950,000.00
Variable cost(72,000*5.5) $             396,000.00
Total Manufacuring cost(A) $         1,346,000.00
Total Machine hours(B)                   72,000.00
Predetermined Overhead Rate (C )=(A)/(B) $                     18.694

b)

Calculation of total manufacturing cost assigned
Job D-70 Job C-200
Direct Material Cost $       700,000 $       520,000
Direct Labor Cost $       390,000 $       430,000
Manufacturing Overhead $       579,528 $       766,472
Total Cost Assigned $    1,669,528 $    1,716,472

Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students