Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger...
70.2K
Verified Solution
Question
Accounting
Entry for Jobs Completed; Cost of Unfinished Jobs
The following account appears in the ledger prior to recognizing the jobs completed in January:
Work in Process | ||
Balance, January 1 | $11,190 | |
Direct materials | 90,970 | |
Direct labor | 98,140 | |
Factory overhead | 51,590 |
Jobs finished during January are summarized as follows:
Job 210 | $45,340 | Job 224 | $52,900 | |
Job 216 | 27,710 | Job 230 | 95,720 |
Question Content Area
a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank.
Question Content Area
b. Determine the cost of the unfinished jobs at January 31. $fill in the blank 3942baff9ff4fbb_1
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.