eBook Question Content Area Basics of Variance Analysis, Variable Inputs Basuras Waste Disposal Company has...
90.2K
Verified Solution
Link Copied!
Question
Accounting
eBook
Question Content Area
Basics of Variance Analysis, Variable Inputs
Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage and trash from residential customers. To facilitate the collection, Basuras places a large plastic container with each household. Because of wear and tear, growth, and other factors, Basuras places about 230,000 new containers each year (about 20% of the total households). Several years ago, Basuras decided to manufacture its own containers as a cost-saving measure. A strategically located plant involved in this type of manufacturing was acquired. To help ensure cost efficiency, a standard cost system was installed in the plant. The following standards have been established for the product's variable inputs:
Standard Quantity
Standard Price (rate in $)
Standard Cost
Direct materials
12 lbs.
$ 3.5
$42
Direct labor
1.7 hrs.
13
22.1
Variable overhead
1.7 hrs.
5
8.5
Total
$64.1
During the first week in January, Basuras had the following actual results:
Units produced
10,000
Actual labor costs
$228,800
Actual labor hours
17,600
Materials purchased and used
118,000
lbs. @ $3.55
Actual variable overhead costs
$ 110,500
The purchasing agent located a new source of slightly higher-quality plastic, and this material was used during the first week in January. Also, a new manufacturing process was implemented on a trial basis. The new process required a slightly higher level of skilled labor. The higher-quality material has no effect on labor utilization. However, the new manufacturing process was expected to reduce materials usage by 0.25 pound per container.
Required:
1. Conceptual Connection: Compute the materials price and usage variances. Assume that the 0.25 pound per container reduction of materials occurred as expected and that the remaining effects are all attributable to the higher-quality material. Would you recommend that the purchasing agent continue to buy this quality, or should the usual quality be purchased? Assume that the quality of the end product is not affected significantly.
Price
$fill in the blank 1
FavorableUnfavorableNeitherUnfavorable
Usage
$fill in the blank 3
FavorableUnfavorableNeitherFavorable
Select the effect.
The new process saves money.The new process costs more money.The new process saves money.
Enter the net amount of the effect.
$fill in the blank 6
Select the correct decision.
Use the higher-quality material.Use the original material.Use the original material.
2. Conceptual Connection: Compute the labor rate and efficiency variances. Assuming that the labor variances are attributable to the new manufacturing process, should it be continued or discontinued? In answering, consider the new process's materials reduction effect as well. If an amount is zero, enter "0".
Rate
$fill in the blank 8
FavorableUnfavorableNeitherNeither
Efficiency
$fill in the blank 10
FavorableUnfavorableNeitherUnfavorable
Select the effect.
The new process saves money.The new process costs more money.The new process costs more money.
Enter the overall net amount of the effect.
$fill in the blank 13
Select the correct decision.
Discontinue the new process.Continue the new process.Discontinue the new process.
3. Conceptual Connection: Refer to Requirement 2. Suppose that the industrial engineer argued that the new process should not be evaluated after only one week. His reasoning was that it would take at least a week for the workers to become efficient with the new approach. Suppose that the production is the same the second week and that the actual labor hours were 13,000 and the labor cost was $169,000. Should the new process be adopted? Assume the variances are attributable to the new process. Assuming production of 10,000 units per week, what would be the projected annual savings? (Include the materials reduction effect.) If an amount is zero, enter "0".
Rate
$fill in the blank 15
FavorableUnfavorableNeitherNeither
Efficiency
$fill in the blank 17
FavorableUnfavorableNeitherFavorable
Select the effect.
The new process saves money.The new process costs more money.The new process saves money.
Enter the annual amount of the effect.
$fill in the blank 20
Select the correct decision.
Continue the new process.Discontinue the new process.Continue the new process.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!