During July, the following costs were incurred:
Materials (30,000 units) $24,900
Labour and overheads $20,075
At the beginning of July, there were 15,000 units of work inprogress valued as follows:
Materials (100% complete) $9,000
Labour and overheads (40% complete) $1,250
At the end of July, there were 5,000 units of work-in-progress.They were 100% complete for materials
and 50% complete for labour and overheads.
Using both FIFO approach and Weighted Average approach:
(a) calculate how many units were completed during July
(b) calculate the cost per unit
(c) value the finished items and the closing work-in-progress
(d) prepare a Process Account. (Note: assume no losses)