During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable.

2020 2021 2022
Costs incurred to date $344,000 $709,500 $920,200
Estimated costs to complete 516,000 236,500 0
Billings to date (non-refundable) 258,000 774,000 1,376,000
Collections to date 232,200 696,600 1,225,500

Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020 2021 2022
Gross profit / (loss) $enter a dollar amount $enter a dollar amount $enter a dollar amount

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students